What could this water PPP cost the public side?
A first screen for a utility project team. Enter your own contract figures. You see what the public side pays each year under the contract, what one trigger could add, and how maximum exposure, cash due and expected loss differ.
Your figures stay in this browser. Nothing is sent, saved or added to the page address. Closing the tab clears them.
How the screen works
PPP discussions often mix up three different numbers. The screen keeps them apart, next to the payments the contract already requires.
- Direct commitment
- A payment the contract already requires, such as an availability or capacity payment. It is due if the service is delivered. Only its size can move, for example with indexation.
- Contingent liability
- A payment that happens only if a trigger event occurs, such as revenue falling below a guaranteed floor, the local currency falling against the currency of a foreign loan, or the contract ending early. The trigger, the timing and the size can all be uncertain.
- Maximum exposure
- The most the public side could pay under one undertaking, treating the event as certain in the worst year. It is a ceiling, not a forecast. Some undertakings, such as an exchange-rate guarantee, have no ceiling.
- Cash due
- The payment that falls due under one scenario you choose to test.
- Expected loss
- Cash due multiplied by the probability that the trigger happens. It means something only with a documented probability, so the screen leaves it blank unless you enter one.
The formulas
Payment in year t = annual payment × (1 + indexation) ^ (t − base year)Guarantee cash due = max(0, floor share × base-case revenue − achieved share × base-case revenue)Termination compensation = debt share × outstanding debt + equity share × outstanding equityExchange-rate guarantee cash due = covered share × foreign debt service × guaranteed rate × max(0, market rate ÷ guaranteed rate − 1)Expected loss = probability × cash duePresent value = Σ amount in year n ÷ (1 + discount rate) ^ n
I tested these formulas against an independent reference model on base, stress and boundary cases. The results matched.
What it leaves out: demand modelled with probability distributions, exchange-rate paths that change from year to year, tax, and the project's own debt-service coverage. Those need the full financial model.
For a wider view of fiscal risk across a PPP programme, the IMF and the World Bank publish a free tool, the PPP Fiscal Risk Assessment Model (PFRAM). Read about the PFRAM on the IMF site

Questions about the newsletter, the tools or the case studies?
Write to me or book a short call. Everything here is independent analysis in my own name, not an offer of professional services.
Pick a 30-minute slot. I confirm each request by email, then you receive the Google Meet link.