National Drainage Programme
Buried field drains that protect farmland from waterlogging and salinity, delivered as a national programme in phases over three decades with several lenders.
This case is drafted from official public sources only. Figures are as published by the sources listed at the end, and each paragraph shows the number of its source. What worked, what was hard and the lessons are my reading of that public record.
The problem
Year-round irrigation raised groundwater levels under Egypt's farmland. Waterlogging and soil salinity became clearly visible from the mid-1970s and put yields at risk. [1]
The solution
Field drains buried under the farmland collect surplus water. Collector pipes carry it by gravity to open drains, with pumping stations where gravity is not enough. [1]
The work has run as a national programme in phases since the 1990s. Phase II was approved in 2000 and completed in 2015. Phase III covers 2016 to 2026 and includes renewing networks that are more than 25 years old. [3]
The first phase alone drained about 248,000 hectares for the first time and rehabilitated field drainage on about 63,000 hectares. [1]
The government's project page for phase III lists the renewal of covered drainage on 500,000 feddans and new networks on 100,000 feddans. [4]
WEFE connections
Water
Drainage removes surplus irrigation water and keeps the water table below the root zone, so that irrigation delivers its full benefit. [1, 2]
Energy
Where water cannot leave by gravity, drainage depends on pumping stations. The first phase added USD 37.8 million for pumping station equipment and vehicles, because the system could not function without the pumps. [1]
Food
Drained fields earned more. Income gains attributed to the first phase were 30 per cent in the Delta and 38 per cent in the Nile valley, against a target of 20 per cent. [1]
Ecosystems
The evaluation found the drainage programmes very successful in preventing further salination of the soil, the resource that farming depends on. [1]
Who financed it and how
Each phase combines the national budget with loans and grants from several lenders. In phase III the lenders finance similar works in different geographical areas.
- Phase I, 1993 to 2001
- Investment of EUR 249.4 million, of which EUR 128.5 million was Egypt's own contribution. Led by the World Bank, with a KfW loan of EUR 22.9 million, a KfW grant of EUR 2.7 million and Dutch technical cooperation. [1]
- Phase III, 2016 to 2026
- About USD 250 million from the Islamic Development Bank, KfW, the EU, the African Development Bank and Egypt. The African Development Bank's part is a loan of EUR 50.20 million. [2, 3]
- Farmers
- In the first phase, users repaid the investment cost over 20 years without interest. [1]
What worked
- It delivered at scale. The first phase slightly exceeded its target of about 310,000 hectares, and yield targets for wheat, maize and cotton were met and partly exceeded. [1]
- It reached smallholders. About 370,000 farms with 2.2 million people benefited, and roughly 70 per cent of those farms are smallholdings. [1]
- Local industry built it. Pipe laying was done by Egyptian contractors, and the evaluation rated the quality of construction as good. [1]
- The model lasted. One executing agency has carried successive phases for three decades, and new lenders have joined phase by phase. [1, 2]
- Results were measured the way farmers see them: income on drained fields compared with income on undrained fields. [1]
What was hard
- Implementation of the first phase took two years longer than planned, although the evaluation found no noticeable negative effect. [1]
- Open drains proved harder to maintain than buried pipes. Unsuitable dredging equipment damaged the side slopes and made later maintenance more difficult. [1]
- Part of the technical assistance, a management information system, was designed, tested and documented but did not move into daily use. The evaluation links this to ownership: tools developed by a consultant are adopted only when the team that will run them sees a need for them. [1]
- Funding for operation and maintenance was only just sufficient, and users did not contribute to running costs. [1]
Lessons to replicate
Run drainage as a programme, not a project
Networks age, so renewal never ends. A standing programme with one executing agency and a rolling plan lets lenders join phase by phase without redesigning the approach.
Measure farm income, with and without
Kilometres of pipe do not make the case for the next phase. Compare incomes and yields on drained and undrained fields, and publish the result.
Budget maintenance of open drains from day one
Buried pipes last when the open drains they feed are kept in shape. Fund the right equipment and routine maintenance as part of the investment.
Agree early how users take part and share costs
Involve farmers in planning, implementation and operation, and settle how running costs are shared before the works begin. Build management tools with the team that will use them.
Sources
Official pages and documents. Each link opens in a new tab.
- 1. Ex-post evaluation: Egypt, National Drainage Programme, 2004Open source ↗
- 2. News release on the loan for the National Drainage Programme, June 2015Open source ↗