Alexandria West wastewater treatment plant

AlexandriaFinancing signed

A large city plant is upgraded from primary to secondary treatment, expanded, and designed to make energy from its own sludge.

This case is drafted from official public sources only. Figures are as published by the sources listed at the end, and each paragraph shows the number of its source. What worked, what was hard and the lessons are my reading of that public record.

The problem

The Alexandria West plant is designed to serve 1.8 million people. Its treatment was limited to the primary stage. [3]

Partly treated effluent flowed for decades towards Lake Maryout, El Mex Bay and finally the Mediterranean. The project's impact assessment describes the lake as being in an advanced state of environmental degradation. [3, 4]

The solution

Upgrade the plant from primary to secondary (biological) treatment and expand it from about 460,000 to 600,000 cubic metres a day, sized for needs up to 2050. [2, 4]

Add sludge treatment with digesters, so that biogas from the sludge produces energy for the plant. [2, 3]

All works take place inside the boundary of the existing plant. [3]

WEFE connections

Water

Secondary treatment and more capacity for a plant that serves 1.8 million people. [3]

Energy

Digesters turn sludge into biogas, which limits the plant's own energy use. The EIB estimates a saving of 54 kilotonnes of CO2 equivalent a year against current emissions. [2, 3]

Food

Treated effluent could later become a source of irrigation water, and cleaner water is expected to help fisheries. Reuse itself is a separate, future project. [3, 4]

Ecosystems

Less pollution in Lake Maryout, El Mex Bay and the Mediterranean. [1, 3]

Who financed it and how

A loan from one bank, blended with an EU investment grant, after preparation that was itself funded by grants.

European Investment Bank
Loan of EUR 120 million, signed on 31 December 2019. [1, 2]
European Union
Investment grant of EUR 20.05 million, signed through the EIB in March 2022. Project preparation was itself funded by grants. [1, 2]

The EIB project page puts the approximate total cost at EUR 185 million. [1]

What worked

  • Building inside the existing plant meant no land acquisition, a design with no resettlement, and construction impacts that stay on the site. [3]
  • Energy was designed in from the start. The feasibility work tested whether digesters and energy recovery pay for themselves, and confirmed that they do under projected electricity tariffs. [4]
  • Preparation was funded and published before the loan. The impact assessment was public in 2018 and the loan followed at the end of 2019. [1, 4]
  • Consultation was used to settle scope. Participants asked for effluent reuse to be added. The answer was clear: reuse matters, and it will be a separate project. [4]

What was hard

  • A plant upgrade does not restore a lake by itself. The assessment notes that the channels between the plant and the main drain also need work, to keep polluted water out of the lake in future. [4]
  • Reuse for farming stayed out of scope. The land set aside for effluent irrigation lies about 70 km to the west, no transfer infrastructure exists yet, and reuse needs extra treatment. Its economic case still had to be evaluated. [4]
  • The case for energy recovery depends on electricity prices. It was justified under projected tariffs, so it is worth testing again when those change. [4]
  • Sludge needs a dependable outlet. The assessment records a period when a planned industrial use had not started and sludge accumulated, until composting for farmers was restarted. [4]
  • Financing came in steps over several years: project summary in 2018, loan signature at the end of 2019, grant signature in March 2022. [1]

Lessons to replicate

  1. Upgrade on the existing site where you can

    Staying inside the fence of a working plant removes land and resettlement questions from the critical path. Check early that the design fits the site.

  2. Design energy recovery with the treatment

    Decide on digesters and biogas at feasibility stage, not later. Test the choice at realistic electricity tariffs and say which tariff makes it viable.

  3. Name what is out of scope

    If reuse is not financed, say so, and define it as the next project with its own transfer, treatment and costs. A promised benefit without a budget weakens the investment case.

  4. Plan more than one outlet for sludge

    Sludge is produced every day. Keep at least two tested routes, for example energy and compost, so that a change in one buyer does not stop the plant's logistics.

Your project

Try the same type of project in the translator

Working on a similar project? Choose "Wastewater treatment and reuse" in the project translator and answer ten short questions. You get the WEFE connections, an investment case in six parts and the questions to answer next.

Open the translator →

Sources

Official pages and documents. Each link opens in a new tab.

  1. 1. Project page: Alexandria West wastewater treatment plant extension (20170089)European Investment Bank
    Open source ↗
  2. 2. Press release on the upgrade and expansion loan, February 2020European Investment Bank
    Open source ↗
  3. 3. Environmental and Social Data Sheet: Alexandria West extension and upgrade, 2018European Investment Bank
    Open source ↗
  4. 4. Environmental and Social Impact Assessment from the feasibility study, 2018, published in the EIB public registerEuropean Investment Bank
    Open source ↗
Get in touch

Questions about the newsletter, the tools or the case studies?

Write to me or book a short call. Everything here is independent analysis in my own name, not an offer of professional services.

Pick a 30-minute slot. I confirm each request by email, then you receive the Google Meet link.